Open Budget Kenya

 

Retrofitting of Mini Grids - 2025

State Department

Ministry of Energy

Programme

Power Transmission and Distribution

Sub Programme

National Grid System

Allocation:

KES 320,020,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2025)

Target Yr (2026)

Target Yr (2027)

Power transmission services

No of minigrids retrofitted

15

3

8

Power transmission services

No of minigrids retrofitted


2025

15

2026

3

2027

8

Previous Year Allocations

Num

Year

Total

1

2025

KES 320,020,000.00

2

2024

KES 691,000,000.00

3

2023

KES 1,765,000,000.00

4

2022

KES 1,193,000,000.00

5

2021

KES 1,800,000,000.00


Total Allocation KES 320,020,000.00

Total Allocation KES 691,000,000.00

Total Allocation KES 1,765,000,000.00

Total Allocation KES 1,193,000,000.00

Total Allocation KES 1,800,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
National Grid System

Km of Transmission Lines Constructed: 248


KES 5,879,816,289.00

(2025)

SonduHomabay Ndhiwa Awendo Electrification Project-BETA

Percentage completion of 105km 132 kV single circuit transmission line and associated substations: 80


KES 693,696,723.00

(2025)

Olkaria Lessos Kisumu Power Lines Construction Project

Percentage completion of transmission line and associated substations: 50


KES 506,086,029.00

(2025)