Open Budget Kenya

 

Rabai - Kilifi Transmission Line - 2022

State Department

Ministry of Energy

Programme

Power Transmission and Distribution

Sub Programme

National Grid System

Allocation:

KES 1,063,000,000.00 (D)

Key Performance Indicators

Key Output

KPI

Target Yr (2022)

Target Yr (2023)

Target Yr (2024)

Power transmission infrastructure

Percentage completion of 132 kV Rabai - Kilifi transmission line and the associated substations

70

100

100

Previous Year Allocations

Num

Year

Recurrent

Development

Total

1

2021

KES 0.00

KES 1,030,000,000.00

KES 1,030,000,000.00

2

2022

KES 0.00

KES 1,063,000,000.00

KES 1,063,000,000.00

3

2023

KES 0.00

KES 1,078,000,000.00

KES 1,078,000,000.00

4

2024

KES 0.00

KES 376,800,000.00

KES 376,800,000.00

Budgets