Open Budget Kenya

 

Electrification of Food Processing Plants - 2021

State Department

Ministry of Energy

Programme

Power Transmission and Distribution

Sub Programme

National Grid System

Allocation:

KES 100,000,000.00 (D)

Key Performance Indicators

Key Output

KPI

Target Yr (2021)

Target Yr (2022)

Target Yr (2023)

Electrified food processing plants

No. of food processing plants electrified.

16

-

-

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project

Previous Year Allocations

Num

Year

Recurrent

Development

Total

1

2022

KES 0.00

KES 269,000,000.00

KES 269,000,000.00

2

2021

KES 0.00

KES 100,000,000.00

KES 100,000,000.00

Budgets
Related Projects
National Grid System

No. of public awareness forums conducted: 30


KES 3,245,000,000.00

(2021)

Nanyuki-Isiolo- Meru

% completion: 100


KES 340,000,000.00

(2021)

SonduHomabay Ndhiwa Awendo Electrification Project

% completion: 100


KES 514,000,000.00

(2021)

© 2025 Copyright: Open Budget KE
Email: openbudgetke @ gmail.com