Open Budget Kenya

 

Loiyangalani- Marsabit 400 KV Transmission Line - 2021

State Department

Ministry of Energy

Programme

Power Transmission and Distribution

Sub Programme

National Grid System

Allocation:

KES 1,188,000,000.00 (D)

Key Performance Indicators

Key Output

KPI

Target Yr (2021)

Target Yr (2022)

Target Yr (2023)

136km 400kV double circuit Transmission line and associated substations

% completion

20

100

100

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project

Previous Year Allocations

Num

Year

Recurrent

Development

Total

1

2024

KES 0.00

KES 612,700,000.00

KES 612,700,000.00

2

2022

KES 0.00

KES 2,434,000,000.00

KES 2,434,000,000.00

3

2021

KES 0.00

KES 1,188,000,000.00

KES 1,188,000,000.00

Budgets
Related Projects
National Grid System

No. of public awareness forums conducted: 30


KES 3,245,000,000.00

(2021)

Nanyuki-Isiolo- Meru

% completion: 100


KES 340,000,000.00

(2021)

SonduHomabay Ndhiwa Awendo Electrification Project

% completion: 100


KES 514,000,000.00

(2021)