Olkaria 1AU & IV Turbine Uprating - 2025 |
|
---|---|
State Department |
|
Programme |
|
Sub Programme |
|
Allocation: |
KES 20,000,000.00 (D) |
Key Performance Indicators
Key Output |
KPI |
Target Yr (2025) |
Target Yr (2026) |
Target Yr (2027) |
---|---|---|---|---|
Geothermal Power Services |
Percentage (%) Completion of 40MW Olkaria 1 Turbine Uprating |
12 |
70 |
70 |
User Uploads
Previous Year Allocations
Num |
Year |
Recurrent |
Development |
Total |
---|---|---|---|---|
1 |
KES 0.00 |
KES 20,000,000.00 |
KES 20,000,000.00 |
|
2 |
KES 0.00 |
KES 1,631,250,000.00 |
KES 1,631,250,000.00 |
|
3 |
KES 0.00 |
KES 2,100,000,000.00 |
KES 2,100,000,000.00 |
Percentage (%) Completion of 63MW Olkaria 1 Rehabilitation Power plant: 80
KES 1,846,102,298.00
(2025)