Sustain Energy Fund for Africa (SEFA) Devpt of Utility Run Super ESCO - 2025 |
|
|---|---|
|
State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 100,000,000.00 (D) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2025) |
Target Yr (2026) |
Target Yr (2027) |
|---|---|---|---|---|
Power transmission services |
% completion of developed super Esco |
100 |
100 |
100 |
Power transmission services
% completion of developed super Esco
2025
100
2026
100
2027
100
Previous Year Allocations
Num |
Year |
Total |
|---|---|---|
1 |
KES 100,000,000.00 |
|
2 |
KES 50,000,000.00 |
|
3 |
KES 50,000,000.00 |
|
4 |
KES 50,000,000.00 |
User Uploads
Percentage completion of 105km 132 kV single circuit transmission line and associated substations: 80
KES 693,696,723.00
(2025)
Percentage completion of transmission line and associated substations: 50
KES 506,086,029.00
(2025)