Open Budget Kenya

 

Sustain Energy Fund for Africa (SEFA) Devpt of Utility Run Super ESCO - 2025

State Department

Ministry of Energy

Programme

Power Transmission and Distribution

Sub Programme

National Grid System

Allocation:

KES 100,000,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2025)

Target Yr (2026)

Target Yr (2027)

Power transmission services

% completion of developed super Esco

100

100

100

Power transmission services

% completion of developed super Esco


2025

100

2026

100

2027

100

Previous Year Allocations

Num

Year

Total

1

2025

KES 100,000,000.00

2

2024

KES 50,000,000.00

3

2023

KES 50,000,000.00

4

2022

KES 50,000,000.00


Total Allocation KES 100,000,000.00

Total Allocation KES 50,000,000.00

Total Allocation KES 50,000,000.00

Total Allocation KES 50,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
National Grid System

Km of Transmission Lines Constructed: 248


KES 5,879,816,289.00

(2025)

SonduHomabay Ndhiwa Awendo Electrification Project-BETA

Percentage completion of 105km 132 kV single circuit transmission line and associated substations: 80


KES 693,696,723.00

(2025)

Olkaria Lessos Kisumu Power Lines Construction Project

Percentage completion of transmission line and associated substations: 50


KES 506,086,029.00

(2025)

© 2025 Copyright: Open Budget KE
Email: openbudgetke @ gmail.com