Kenya Transmission Network Improvement Project - 2025 |
|
|---|---|
|
State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 1,725,990,971.00 (D) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2025) |
Target Yr (2026) |
Target Yr (2027) |
|---|---|---|---|---|
Power transmission services |
Percentage completion of transmission line and associated substations |
70 |
100 |
100 |
Power transmission services
Percentage completion of transmission line and associated substations
2025
70
2026
100
2027
100
Previous Year Allocations
User Uploads
Percentage completion of 105km 132 kV single circuit transmission line and associated substations: 80
KES 693,696,723.00
(2025)
Percentage completion of transmission line and associated substations: 50
KES 506,086,029.00
(2025)