Open Budget Kenya

 

Public Participation Projects - 2024

State Department

Ministry of Energy

Programme

Power Transmission and Distribution

Sub Programme

Rural Electrification

Allocation:

KES 0.00 (D+R)

Previous Year Allocations

Num

Year

Total

1

2024

KES 0.00


Total Allocation KES 0.00
Changes in Allocations

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2024)

Target Yr (2025)

Target Yr (2026)

Power connectivity

% of completion

Power connectivity

% of completion


2024

2025

2026

Related Projects
National Grid System

Technical Validation reports: 4


KES 5,602,191,396.00

(2024)

Nanyuki-Isiolo- Meru-BETA

Percentage completion of 105km 132 kV single circuit transmission line and associated substations: 100


KES 96,600,000.00

(2024)

SonduHomabay Ndhiwa Awendo Electrification Project-BETA

Percentage completion of 105km 132 kV single circuit transmission line and associated substations: 100


KES 373,800,000.00

(2024)