Kimahuri Milk Cooling Plant Project - 2022 |
|
|---|---|
|
State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 30,000,000.00 (D) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2022) |
Target Yr (2023) |
Target Yr (2024) |
|---|---|---|---|---|
Kimahuri Milk Cooling Plant |
% completion of premises |
100 |
- |
- |
Kimahuri Milk Cooling Plant |
No. of milk plants delivered |
1 |
- |
- |
Kimahuri Milk Cooling Plant |
No. of trucks delivered |
1 |
- |
- |
Kimahuri Milk Cooling Plant
% completion of premises
2022
100
2023
-
2024
-
Kimahuri Milk Cooling Plant
No. of milk plants delivered
2022
1
2023
-
2024
-
Kimahuri Milk Cooling Plant
No. of trucks delivered
2022
1
2023
-
2024
-
Previous Year Allocations
Num |
Year |
Total |
|---|---|---|
1 |
KES 30,000,000.00 |
User Uploads
No. of Electronic Documents and Records Management System procured, installed and maintained: 1
KES 270,301,383.00
(2022)