Forest Fire Protection Management Project - 2024 |
|
|---|---|
|
State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 10,000,000.00 (D) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2024) |
Target Yr (2025) |
Target Yr (2026) |
|---|---|---|---|---|
Forest fire Management |
KM of fire breaks/lines maintained |
450 |
950 |
1200 |
Forest fire Management |
No. of assorted equipments |
100 |
120 |
125 |
Forest fire Management
KM of fire breaks/lines maintained
2024
450
2025
950
2026
1200
Forest fire Management
No. of assorted equipments
2024
100
2025
120
2026
125
Previous Year Allocations
User Uploads
Ha of degraded water tower rehabilitated: 700
KES 55,000,000.00
KES 27,500,000.00
(2024)
Ha of bamboo stock established within water tower ecosystems: 300
KES 75,000,000.00
KES 37,500,000.00
(2024)
Ha. of Landscape restoration: 1.06million
KES 323,000,000.00
KES 262,368,056.00
(2024)