Geothermal generation - 2024 |
|
|---|---|
|
State Department |
|
|
Program |
|
|
Allocation: |
14,154,486,011.00 |
Previous Year Allocations
| Num | Year | Total |
|---|---|---|
| 1 | 2025 | KES 11,578,568,375.00 |
| 2 | 2024 | KES 14,154,486,011.00 |
| 3 | 2023 | KES 11,547,921,265.00 |
| 4 | 2022 | KES 18,531,000,000.00 |
| 5 | 2021 | KES 11,121,000,000.00 |
Recurrent Expenses
| Num | Unit | Budget |
|---|---|---|
| 1 | Geothermal and Coal Resource Exploration and Development | KES 1,529,736,011.00 |
Development Expenses
| Num | Unit | Budget |
|---|---|---|
| 1 | Bogoria Silali Geothermal Project | KES 4,134,000,000.00 |
| 2 | Ol Karia I Units 1,2,3 Geothermal Power Plant Rehabilitation Project | KES 4,000,000,000.00 |
| 3 | Menengai Geothermal Development Project | KES 2,162,000,000.00 |
| 4 | Olkaria 1AU & IV Turbine Uprating | KES 1,631,250,000.00 |
| 5 | 300MW Suswa geothernal project | KES 570,000,000.00 |
| 6 | East Africa Skills for Transformation & Regional Integration Project | KES 100,000,000.00 |
| 7 | Olkaria I and IV | KES 27,500,000.00 |