Open Budget Kenya

 

Kisii By-Pass Phase II - 2026

State Department

State Department for Infrastructure

Programme

Road Transport

Sub Programme

Construction of Roads and Bridges

Allocation:

KES 42,346,055.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2026)

Target Yr (2027)

Target Yr (2028)

Kisii Bypass Phase II

No of Km Constructed

1.5

3

-

Kisii Bypass Phase II

No of Km Constructed


2026

1.5

2027

3

2028

-

Previous Year Allocations

Num

Year

Total

1

2026

KES 42,346,055.00

2

2025

KES 86,781,075.00

3

2024

KES 100,000,000.00

4

2023

KES 75,000,000.00

5

2022

KES 80,000,000.00

6

2021

KES 100,000,000.00


Total Allocation KES 42,346,055.00

Total Allocation KES 86,781,075.00

Total Allocation KES 100,000,000.00

Total Allocation KES 75,000,000.00

Total Allocation KES 80,000,000.00

Total Allocation KES 100,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
Northern Corridor Transport Improvement Project

No of Km Constructed: 1.5


KES 108,836,105.00

(2026)

Kenya Transport Sector Support Programme

No of Km Constructed: 3


KES 324,957,197.00

(2026)

National Urban Transport Improvement Project (NUTRIP)

No of Km Constructed: 4


KES 912,791,287.00

(2026)