Open Budget Kenya

 

National Grid System - 2024

State Department

Ministry of Energy

Programme

Power Generation

Sub Programme

Development of Nuclear Energy

Allocation:

KES 5,602,191,396.00 (R)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2024)

Target Yr (2025)

Target Yr (2026)

Technical Validation , monitoring and evaluation services

Technical Validation reports

4

4

4

Power transmission infrastructure monitoring reports

No. of quarterly technical transmission line and associated substations reports

4

4

4

Technical Validation , monitoring and evaluation services

Technical Validation reports


2024

4

2025

4

2026

4

Power transmission infrastructure monitoring reports

No. of quarterly technical transmission line and associated substations reports


2024

4

2025

4

2026

4

Previous Year Allocations

Num

Year

Total

1

2025

KES 5,879,816,289.00

2

2024

KES 5,602,191,396.00

3

2023

KES 3,844,711,907.00

4

2022

KES 10,917,000,000.00

5

2021

KES 3,245,000,000.00


Total Allocation KES 5,879,816,289.00

Total Allocation KES 5,602,191,396.00

Total Allocation KES 3,844,711,907.00

Total Allocation KES 10,917,000,000.00

Total Allocation KES 3,245,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
Geothermal and Coal Resource Exploration and Development

No. of Research and Monitoring of Geotechnical Study Reports: 4


KES 1,529,736,011.00

(2024)

Bogoria Silali Geothermal Project

No of Well drilled: 6


KES 4,134,000,000.00

(2024)

Olkaria I and IV

Percentage completion of 83.3MW Olkaria 1 Unit 6 Power plant: 100


KES 27,500,000.00

(2024)