National Grid System - 2025

State Department

Ministry of Energy

Programme

Power Generation

Sub Programme

Development of Nuclear Energy

Allocation:

KES 5,879,816,289.00 (R)

Previous Year Allocations

Num

Year

Total

1

2026

KES 6,183,650,010.00

2

2025

KES 5,879,816,289.00

3

2024

KES 5,602,191,396.00

4

2023

KES 3,844,711,907.00

5

2022

KES 10,917,000,000.00

6

2021

KES 3,245,000,000.00


Total Allocation KES 6,183,650,010.00

Total Allocation KES 5,879,816,289.00

Total Allocation KES 5,602,191,396.00

Total Allocation KES 3,844,711,907.00

Total Allocation KES 10,917,000,000.00

Total Allocation KES 3,245,000,000.00
Changes in Allocations

Project Items

Num

Project

Amount

Year

1

Headquarters

KES 59,682,010.00

2026

2

Kenya Electricity Transmission Company

KES 5,528,000,000.00

2026

3

Nuclear Power and Energy Agency

KES 595,968,000.00

2026

4

Headquarters

KES 45,416,289.00

2025

5

Kenya Electricity Transmission Company

KES 5,343,000,000.00

2025

6

Nuclear Power and Energy Agency

KES 491,400,000.00

2025


2026 KES 59,682,010.00

2026 KES 5,528,000,000.00

2026 KES 595,968,000.00

2025 KES 45,416,289.00

2025 KES 5,343,000,000.00

2025 KES 491,400,000.00

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2025)

Target Yr (2026)

Target Yr (2027)

Power transmission services

Km of Transmission Lines Constructed

248

596

898

Power transmission services

No. of quarterly technical transmission line and associated substations reports

4

4

4

Power transmission services

Km of Transmission Lines Constructed


2025

248

2026

596

2027

898

Power transmission services

No. of quarterly technical transmission line and associated substations reports


2025

4

2026

4

2027

4

Related Projects
Geothermal and Coal Resource Exploration and Development

Percentage (%) Completion of 63MW Olkaria 1 Rehabilitation Power plant: 80


KES 1,846,102,298.00

(2025)

Bogoria Silali Geothermal Project

No of Well drilled: 8


KES 2,806,000,000.00

(2025)

Menengai Geothermal Development Project

No of Well drilled: 4


KES 1,950,000,000.00

(2025)