National Grid System - 2025 |
|
|---|---|
|
State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 5,879,816,289.00 (R) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2025) |
Target Yr (2026) |
Target Yr (2027) |
|---|---|---|---|---|
Power transmission services |
Km of Transmission Lines Constructed |
248 |
596 |
898 |
Power transmission services |
No. of quarterly technical transmission line and associated substations reports |
4 |
4 |
4 |
Power transmission services
Km of Transmission Lines Constructed
2025
248
2026
596
2027
898
Power transmission services
No. of quarterly technical transmission line and associated substations reports
2025
4
2026
4
2027
4
Previous Year Allocations
Num |
Year |
Total |
|---|---|---|
1 |
KES 5,879,816,289.00 |
|
2 |
KES 5,602,191,396.00 |
|
3 |
KES 3,844,711,907.00 |
|
4 |
KES 10,917,000,000.00 |
|
5 |
KES 3,245,000,000.00 |
User Uploads
Percentage (%) Completion of 63MW Olkaria 1 Rehabilitation Power plant: 80
KES 1,846,102,298.00
(2025)