Open Budget Kenya

 

Bogoria Silali Geothermal Project - 2024

State Department

Ministry of Energy

Programme

Power Generation

Sub Programme

Geothermal generation

Allocation:

KES 4,134,000,000.00 (D)

Key Performance Indicators

Key Output

KPI

Target Yr (2024)

Target Yr (2025)

Target Yr (2026)

Bogoria silali geothermal power project

No of Well drilled

6

8

8

Bogoria silali geothermal power project

MW of steam equivalent( cumulative)

122

82

82

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project

Previous Year Allocations

Num

Year

Recurrent

Development

Total

1

2025

KES 0.00

KES 2,806,000,000.00

KES 2,806,000,000.00

2

2024

KES 0.00

KES 4,134,000,000.00

KES 4,134,000,000.00

3

2023

KES 0.00

KES 4,723,000,000.00

KES 4,723,000,000.00

4

2022

KES 0.00

KES 5,771,000,000.00

KES 5,771,000,000.00

5

2021

KES 0.00

KES 2,398,000,000.00

KES 2,398,000,000.00

Budgets
Related Projects
Geothermal and Coal Resource Exploration and Development

No. of Research and Monitoring of Geotechnical Study Reports: 4


KES 1,529,736,011.00

(2024)

Olkaria I and IV

Percentage completion of 83.3MW Olkaria 1 Unit 6 Power plant: 100


KES 27,500,000.00

(2024)

Menengai Geothermal Development Project

No of Well drilled: 3


KES 2,162,000,000.00

(2024)