Last Mile Electricity Connectivity-BETA - 2026

State Department

Ministry of Energy

Programme

Power Transmission and Distribution

Sub Programme

National Grid System

Allocation:

KES 0.00 (D+R)

Previous Year Allocations

Num

Year

Total

1

2026

KES 0.00

2

2025

KES 4,096,380,422.00

3

2024

KES 3,388,000,000.00

4

2023

KES 11,400,000,000.00

5

2022

KES 5,803,000,000.00

6

2021

KES 6,493,000,000.00


Total Allocation KES 0.00

Total Allocation KES 4,096,380,422.00

Total Allocation KES 3,388,000,000.00

Total Allocation KES 11,400,000,000.00

Total Allocation KES 5,803,000,000.00

Total Allocation KES 6,493,000,000.00
Changes in Allocations

Project Items

Num

Project

Amount

Year

1

Headquarters

KES 0.00

2026

2

Headquarters

KES 4,096,380,422.00

2025

3

Three Last Mile Projects in Ruiru Constituency

KES 0.00

2025


2026 KES 0.00

2025 KES 4,096,380,422.00

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2026)

Target Yr (2027)

Target Yr (2028)

Power transmission infrastructure

No. of new customers connected to electricity

450000

450000

500000

Power transmission infrastructure

No. of new customers connected to electricity


2026

450000

2027

450000

2028

500000

Related Projects
National Grid System

Number of Monitoring and Evaluation Reports: 4


KES 6,183,650,010.00

(2026)

Financial Management and Procurement Services

No. of budget reports: 4


KES 111,372,968.00

(2026)

National System Control Centre & Makindu SS

% completion of transmission line and associated substation: 6


KES 1,904,000,000.00

(2026)