Open Budget Kenya

 

Power Transmission System Improvement project - 2024

State Department

Ministry of Energy

Programme

Power Transmission and Distribution

Sub Programme

National Grid System

Allocation:

KES 490,000,000.00 (D)

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2024)

Target Yr (2025)

Target Yr (2026)

Power transmission infrastructure

Percentage completion of transmission line and associated substations

100

-

-

Power transmission infrastructure

Percentage completion of transmission line and associated substations


2024

100

2025

-

2026

-

Previous Year Allocations

Num

Year

Total

1

2025

KES 699,086,029.00

2

2024

KES 490,000,000.00

3

2023

KES 245,000,000.00

4

2022

KES 160,000,000.00

5

2021

KES 160,000,000.00


Total Allocation KES 699,086,029.00

Total Allocation KES 490,000,000.00

Total Allocation KES 245,000,000.00

Total Allocation KES 160,000,000.00

Total Allocation KES 160,000,000.00
Changes in Allocations

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project
Related Projects
National Grid System

Technical Validation reports: 4


KES 5,602,191,396.00

(2024)

Nanyuki-Isiolo- Meru-BETA

Percentage completion of 105km 132 kV single circuit transmission line and associated substations: 100


KES 96,600,000.00

(2024)

SonduHomabay Ndhiwa Awendo Electrification Project-BETA

Percentage completion of 105km 132 kV single circuit transmission line and associated substations: 100


KES 373,800,000.00

(2024)

© 2025 Copyright: Open Budget KE
Email: openbudgetke @ gmail.com