Open Budget Kenya

 

National Grid System - 2024

State Department

Ministry of Energy

Program

Power Transmission and Distribution

Allocation:

27,371,191,396.00

Previous Year Allocations

Num Year Total
1 2025 KES 31,836,416,828.00
2 2024 KES 27,371,191,396.00
3 2023 KES 33,379,711,907.00
4 2022 KES 62,580,855,000.00
5 2021 KES 48,596,000,000.00

Total Allocation KES 31,836,416,828.00

Total Allocation KES 27,371,191,396.00

Total Allocation KES 33,379,711,907.00

Total Allocation KES 62,580,855,000.00

Total Allocation KES 48,596,000,000.00
Allocations by Year
Sub-Programmes

Recurrent Expenses

Num Unit Budget
1 National Grid System KES 5,602,191,396.00

Recurrent Budget KES 5,602,191,396.00

Development Expenses

Num Unit Budget
1 Kenya Off-Grid Solar Access Project for Underserved Counties (KOSAP) KES 4,755,000,000.00
2 National System Control Centre & Makindu SS KES 4,189,400,000.00
3 Last Mile Electricity Connectivity-BETA KES 3,388,000,000.00
4 Kenya Green Resillient Expansion of Energy KES 2,000,000,000.00
5 220KV Kamburu - Embu - Thika Transmission Line KES 1,934,800,000.00
6 Electrification of Economic Zones KES 1,564,400,000.00
7 Rural Electrification Schemes KES 840,700,000.00
8 Eastern Electricity Highway Project (Ethiopia- Kenya Interconnector) KES 746,800,000.00
9 Retrofitting of Mini Grids KES 691,000,000.00
10 Loiyangalani- Marsabit 400 KV Transmission Line KES 612,700,000.00
11 220kV Marsabit - Isiolo Transmission Line KES 612,700,000.00
12 Kenya Power Transmission Expansion Project KES 539,200,000.00
13 Power Transmission System Improvement project KES 490,000,000.00
14 Olkaria Lessos Kisumu Power Lines Construction Project KES 451,500,000.00
15 Rabai - Kilifi Transmission Line-BETA KES 376,800,000.00
16 SonduHomabay Ndhiwa Awendo Electrification Project-BETA KES 373,800,000.00
17 Multi-National Kenya-TZ Power Interconnection Project-BETA KES 292,900,000.00
18 Mariakani Substation-BETA KES 275,000,000.00
19 Street-lighting KES 161,000,000.00
20 Machakos - Konza - Kajiado - Namanga KES 140,000,000.00
21 Turkwell- Ortum- Kitale KES 109,200,000.00
22 Reinforcement of Electricity Transmission Network (RETNET) KES 107,000,000.00
23 Nanyuki-Isiolo- Meru-BETA KES 96,600,000.00
24 Narok - Bomet- BETA KES 75,600,000.00
25 Sustain Energy Fund for Africa (SEFA) Devpt of Utility Run Super ESCO KES 50,000,000.00
26 Nairobi 220KV Ring KES 26,600,000.00
27 Electrification of Government Housing Schemes KES 13,300,000.00

Development Budget KES 4,189,400,000.00

Development Budget KES 3,388,000,000.00

Development Budget KES 2,000,000,000.00

Development Budget KES 1,934,800,000.00

Development Budget KES 1,564,400,000.00

Development Budget KES 840,700,000.00

Development Budget KES 691,000,000.00

Development Budget KES 612,700,000.00

Development Budget KES 612,700,000.00

Development Budget KES 539,200,000.00

Development Budget KES 490,000,000.00

Development Budget KES 451,500,000.00

Development Budget KES 376,800,000.00

Development Budget KES 373,800,000.00

Development Budget KES 292,900,000.00

Development Budget KES 275,000,000.00

Development Budget KES 161,000,000.00

Development Budget KES 140,000,000.00

Development Budget KES 109,200,000.00

Development Budget KES 107,000,000.00

Development Budget KES 96,600,000.00

Development Budget KES 75,600,000.00

Development Budget KES 26,600,000.00

Development Budget KES 13,300,000.00
© 2025 Copyright: Open Budget KE