220kV Marsabit - Isiolo Transmission Line - 2024

State Department

Ministry of Energy

Programme

Power Transmission and Distribution

Sub Programme

National Grid System

Allocation:

KES 612,700,000.00 (D)

Key Performance Indicators

Key Output

KPI

Target Yr (2024)

Target Yr (2025)

Target Yr (2026)

Power transmission infrastructure

Percentage completion of transmission line and associated substations

10

60

60

Previous Year Allocations

Num

Year

Recurrent

Development

Total

1

2021

KES 0.00

KES 512,000,000.00

KES 512,000,000.00

2

2022

KES 0.00

KES 1,800,000,000.00

KES 1,800,000,000.00

3

2024

KES 0.00

KES 612,700,000.00

KES 612,700,000.00

Budgets