Geothermal Projects - 2023 |
|
|---|---|
|
State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 300,000,000.00 (D) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2023) |
Target Yr (2024) |
Target Yr (2025) |
|---|---|---|---|---|
Geothermal energy resources |
Geo-technical Study Reports |
2 |
2 |
2 |
Geothermal energy resources |
Geothermal Resources Licencees Compliance Report |
1 |
2 |
2 |
Geothermal energy resources |
Percentage (%) Completion Geo-portal |
100 |
- |
- |
Geothermal energy resources |
Coal strategy |
1 |
- |
- |
Power generation capacity through coal resources |
Percentage (%)Completion of Concessioning of Block A&B in Mui Basin |
75 |
90 |
100 |
Power generation capacity through coal resources |
Lamu Power Plant Stakeholders engagement reports |
17 |
20 |
22 |
Power generation capacity through coal resources |
% completion of Survey, mapping and repair of coal drill holes in Mui Basin |
70 |
100 |
- |
Power generation capacity through coal resources |
Feasibility study (Coal) |
1 |
1 |
1 |
Geothermal energy resources
Geo-technical Study Reports
2023
2
2024
2
2025
2
Geothermal energy resources
Geothermal Resources Licencees Compliance Report
2023
1
2024
2
2025
2
Geothermal energy resources
Percentage (%) Completion Geo-portal
2023
100
2024
-
2025
-
Geothermal energy resources
Coal strategy
2023
1
2024
-
2025
-
Power generation capacity through coal resources
Percentage (%)Completion of Concessioning of Block A&B in Mui Basin
2023
75
2024
90
2025
100
Power generation capacity through coal resources
Lamu Power Plant Stakeholders engagement reports
2023
17
2024
20
2025
22
Power generation capacity through coal resources
% completion of Survey, mapping and repair of coal drill holes in Mui Basin
2023
70
2024
100
2025
-
Power generation capacity through coal resources
Feasibility study (Coal)
2023
1
2024
1
2025
1
Previous Year Allocations
Num |
Year |
Total |
|---|---|---|
1 |
KES 160,000,000.00 |
|
2 |
KES 110,000,000.00 |
|
3 |
KES 300,000,000.00 |
|
4 |
KES 300,000,000.00 |
|
5 |
KES 74,000,000.00 |
User Uploads
Geotechical Study Reports: 2
KES 1,904,921,265.00
(2023)
Percentage completion of 83.3MW Olkaria 1 Unit 6 Power plant: 100
KES 1,000,000,000.00
(2023)