Resource Development for Nuclear Programme - 2025 |
|
|---|---|
|
State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 17,719,463.00 (D) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2025) |
Target Yr (2026) |
Target Yr (2027) |
|---|---|---|---|---|
Nuclear power services |
No. of persons trained on Nuclear energy |
110 |
150 |
100 |
Nuclear power services |
% completion of nuclear research reactor project |
60 |
70 |
60 |
Nuclear power services |
% completion of public information centres in Nairobi and Kilifi counties |
100 |
150 |
80 |
Nuclear power services
No. of persons trained on Nuclear energy
2025
110
2026
150
2027
100
Nuclear power services
% completion of nuclear research reactor project
2025
60
2026
70
2027
60
Nuclear power services
% completion of public information centres in Nairobi and Kilifi counties
2025
100
2026
150
2027
80
Previous Year Allocations
Num |
Year |
Total |
|---|---|---|
1 |
KES 17,719,463.00 |
|
2 |
KES 105,000,000.00 |
|
3 |
KES 80,000,000.00 |
|
4 |
KES 70,000,000.00 |
|
5 |
KES 10,000,000.00 |
User Uploads
Percentage (%) Completion of 63MW Olkaria 1 Rehabilitation Power plant: 80
KES 1,846,102,298.00
(2025)