Resource Development for Nuclear Programme - 2023 |
|
|---|---|
|
State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 80,000,000.00 (D) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2023) |
Target Yr (2024) |
Target Yr (2025) |
|---|---|---|---|---|
Nuclear energy capacity development |
Number of persons trained on nuclear energy |
90 |
110 |
120 |
Nuclear energy capacity development |
% completion of knowledge management strategy |
100 |
- |
- |
Public information centers on nuclear science and technology |
% completion of two Public Information centers (Nairobi and Kilifi counties) |
20 |
50 |
90 |
Nuclear energy capacity development
Number of persons trained on nuclear energy
2023
90
2024
110
2025
120
Nuclear energy capacity development
% completion of knowledge management strategy
2023
100
2024
-
2025
-
Public information centers on nuclear science and technology
% completion of two Public Information centers (Nairobi and Kilifi counties)
2023
20
2024
50
2025
90
Previous Year Allocations
Num |
Year |
Total |
|---|---|---|
1 |
KES 17,719,463.00 |
|
2 |
KES 105,000,000.00 |
|
3 |
KES 80,000,000.00 |
|
4 |
KES 70,000,000.00 |
|
5 |
KES 10,000,000.00 |
User Uploads
Geotechical Study Reports: 2
KES 1,904,921,265.00
(2023)
Percentage completion of 83.3MW Olkaria 1 Unit 6 Power plant: 100
KES 1,000,000,000.00
(2023)