East Africa Skills for Transformation & Regional Integration Project - 2023 |
|
---|---|
State Department |
|
Programme |
|
Sub Programme |
|
Allocation: |
KES 400,000,000.00 (D) |
Key Performance Indicators
Key Output |
KPI |
Target Yr (2023) |
Target Yr (2024) |
Target Yr (2025) |
---|---|---|---|---|
KenGen geothermal training centre |
Percentage (%) completion of KenGen Geothermal training Centre |
60 |
100 |
100 |
User Uploads
Previous Year Allocations
Num |
Year |
Recurrent |
Development |
Total |
---|---|---|---|---|
1 |
KES 0.00 |
KES 212,000,000.00 |
KES 212,000,000.00 |
|
2 |
KES 0.00 |
KES 100,000,000.00 |
KES 100,000,000.00 |
|
3 |
KES 0.00 |
KES 400,000,000.00 |
KES 400,000,000.00 |
|
4 |
KES 0.00 |
KES 400,000,000.00 |
KES 400,000,000.00 |
|
5 |
KES 0.00 |
KES 414,000,000.00 |
KES 414,000,000.00 |
Geotechical Study Reports: 2
KES 1,904,921,265.00
(2023)
Percentage completion of 83.3MW Olkaria 1 Unit 6 Power plant: 100
KES 1,000,000,000.00
(2023)