Ol Karia I Units 1,2,3 Geothermal Power Plant Rehabilitation Project - 2022 |
|
|---|---|
|
State Department |
|
|
Programme |
|
|
Sub Programme |
|
|
Allocation: |
KES 5,559,000,000.00 (D) |
Key Performance Indicators (Targets)
Key Output |
KPI |
Target Yr (2022) |
Target Yr (2023) |
Target Yr (2024) |
|---|---|---|---|---|
Power generation capacity (MW) |
Percentage completion of 6 MW power plant |
45 |
70 |
100 |
Power generation capacity (MW)
Percentage completion of 6 MW power plant
2022
45
2023
70
2024
100
Previous Year Allocations
Num |
Year |
Total |
|---|---|---|
1 |
KES 4,505,000,000.00 |
|
2 |
KES 4,000,000,000.00 |
|
3 |
KES 0.00 |
|
4 |
KES 5,559,000,000.00 |
|
5 |
KES 2,487,000,000.00 |
User Uploads
Geothermal Resources Licencees Compliance Report: 1
KES 1,907,000,000.00
(2022)