Open Budget Kenya

 

Ol Karia I Units 1,2,3 Geothermal Power Plant Rehabilitation Project - 2025

State Department

Ministry of Energy

Programme

Power Generation

Sub Programme

Geothermal generation

Allocation:

KES 4,505,000,000.00 (D)

Previous Year Allocations

Num

Year

Total

1

2025

KES 4,505,000,000.00

2

2024

KES 4,000,000,000.00

3

2023

KES 0.00

4

2022

KES 5,559,000,000.00

5

2021

KES 2,487,000,000.00


Total Allocation KES 4,505,000,000.00

Total Allocation KES 4,000,000,000.00

Total Allocation KES 0.00

Total Allocation KES 5,559,000,000.00

Total Allocation KES 2,487,000,000.00
Changes in Allocations

Project Items

Num

Project

Amount

Year

1

Ol Karia I Units 1,2,3 Geothermal Power Plant Rehabilitation Project  

KES 0.00

2026

2

Ol Karia I Units 1,2,3 Geothermal Power Plant Rehabilitation Project

KES 4,505,000,000.00

2025

Key Performance Indicators (Targets)

Key Output

KPI

Target Yr (2025)

Target Yr (2026)

Target Yr (2027)

Geothermal Power Services

Percentage (%) Completion of 63MW Olkaria 1 Rehabilitation Power plant

80

95

100

Geothermal Power Services

Percentage (%) Completion of 63MW Olkaria 1 Rehabilitation Power plant


2025

80

2026

95

2027

100

Related Projects
Geothermal and Coal Resource Exploration and Development

Percentage (%) Completion of 63MW Olkaria 1 Rehabilitation Power plant: 80


KES 1,846,102,298.00

(2025)

Bogoria Silali Geothermal Project

No of Well drilled: 8


KES 2,806,000,000.00

(2025)

Menengai Geothermal Development Project

No of Well drilled: 4


KES 1,950,000,000.00

(2025)