Open Budget Kenya

 

Publicity and Advocacy - 2023

State Department

Ministry of Energy

Programme

Power Generation

Sub Programme

Development of Nuclear Energy

Allocation:

KES 213,000,000.00 (D)

Key Performance Indicators

Key Output

KPI

Target Yr (2023)

Target Yr (2024)

Target Yr (2025)

Public education and awareness on nuclear power programme

% level of public awareness and education

50

65

65

User Uploads

Coming Soon.

We will soon allow you (the public) to upload documents you may have about this project

Previous Year Allocations

Num

Year

Recurrent

Development

Total

1

2025

KES 0.00

KES 29,800,915.00

KES 29,800,915.00

2

2024

KES 0.00

KES 91,000,000.00

KES 91,000,000.00

3

2023

KES 0.00

KES 213,000,000.00

KES 213,000,000.00

4

2022

KES 0.00

KES 110,000,000.00

KES 110,000,000.00

5

2021

KES 0.00

KES 100,000,000.00

KES 100,000,000.00

Budgets
Related Projects
Geothermal and Coal Resource Exploration and Development

Geotechical Study Reports: 2


KES 1,904,921,265.00

(2023)

Bogoria Silali Geothermal Project

No. of wells drilled: 15


KES 4,723,000,000.00

(2023)

Olkaria I and IV

Percentage completion of 83.3MW Olkaria 1 Unit 6 Power plant: 100


KES 1,000,000,000.00

(2023)